Ontario new-home buyers may have compensation rights when a builder delays beyond a firm closing or occupancy date, but the Tarion Addendum, notice rules and exceptions matter.
Ontario’s new-home warranty framework includes delayed closing protection for freehold homes and delayed occupancy protection for condominium units. The specific dates and rights are set out in the Tarion Addendum attached to the agreement of purchase and sale.
For a freehold home, Tarion explains that a builder who delays beyond the Firm Closing Date may owe compensation unless an exception applies. For a condominium, similar protection applies where occupancy is delayed beyond the Firm Occupancy Date.
Tarion’s current guidance states that delayed closing or occupancy compensation can be payable up to a maximum of $7,500. The framework includes a fixed amount of $150 per day for direct living expenses, such as accommodation and meals, during a qualifying delay.
Tarion also indicates that buyers may claim other costs caused by the delay, such as moving or storage expenses. Receipts are generally required for those additional expenses, even though receipts are not required for the fixed daily living-expense amount.
Keep every delay notice, amendment, moving invoice, storage receipt and temporary accommodation record. Even where a particular amount does not require receipts, a complete paper trail makes it much easier to assess a claim.
No. The Addendum contains rules governing tentative dates, firm dates, mutual agreements and unavoidable delays. A builder may be permitted to extend dates without compensation where the delay falls within a recognized unavoidable-delay regime and the required notices are given.
Likewise, a purchaser who signs an amendment agreeing to a new date may affect rights that otherwise existed. Buyers should understand the amendment before signing, particularly where it contains release or waiver language.
Tarion’s published consumer guidance notes that, as a general rule, at least 90 days’ written notice is required to change a closing or occupancy date. Delayed closing or occupancy compensation is capped at $7,500 in total. If the builder fails to provide at least 10 days’ notice of the delay, the compensation period is extended so that compensation is payable from 10 days before the Firm Closing or Occupancy Date. At $150 per day that represents $1,500 of compensation, but it counts toward the overall $7,500 maximum rather than being payable on top of it.
The exact effect of any notice depends on the applicable Addendum and the dates in the particular transaction.
Tarion describes unavoidable delays as extraordinary circumstances beyond the builder’s and purchaser’s control, such as certain strikes, fires, explosions, acts of God, civil insurrection, war, terrorism or a pandemic. The Addendum contains the operative rules and notice requirements.
A delayed closing can also affect mortgage commitments, rate holds, leases, moving contracts and the sale of an existing home. The legal warranty claim is only one part of the buyer’s risk. Buyers should coordinate with their lawyer, lender or broker and Realtor as soon as a material delay is announced.
When a client receives a new-build delay notice, encourage them to send the notice and the original Tarion Addendum to their lawyer immediately. The character of the date and wording of any amendment can matter significantly.
Amer Ali Law assists with new-construction purchases across Ontario. See new-construction purchases.
Tarion’s current guidance states that the maximum delayed closing or occupancy compensation is $7,500, subject to the applicable rules.
Tarion says receipts are not required for the fixed direct-living-expense amount, but receipts are required for other claimed expenses such as moving or storage.
There are circumstances in which dates can change, including mutual agreements and unavoidable delays. The Tarion Addendum governs the specific rights.
Not before understanding whether it changes or waives compensation, termination or other contractual rights.
This article is general information about Ontario law and is not legal advice. Reading it does not create a lawyer-client relationship. Every transaction is different, and you should obtain advice about your own circumstances.
AAL Insights by Email
Get new AAL Insights articles, practical transaction guidance and important Ontario legal updates delivered to your inbox.
Get Started
Send us the builder agreement and the Statement of Critical Dates, and we will explain the timing, the deadlines and what to watch.